REF : Solar PV(40.6kWp) system completed and commissioned for Tower A common area

Date:15th April 2024
To:All Residents
From:The Management


Dear Valued Residents,

REF : Solar PV(40.6kWp) system completed and commissioned for Tower A common area

Refer to the matter above, we are pleased to inform you that our Solar PV system was tested and commissioned on 29th February 2024 for Tower A common area.


For the month of March’24, a total of 4.81MWh was generated by the Solar PV system which can be used to power up about 370 units of 18W LED tubes for daily (24 hours) for 31 days.

In general, we can observe more than 10% reduction of kWh usage for both Peak & Mid Peak for the month of Mar-24 compare to the past months (of 31 days) for Block A.
For more information on the Building-Integrated Photovoltaics (BIPV), kindly refer to the following link ; https://www.linkbuild.com.my/projects/what-is-bipv-and-why-is-it-becoming-so-popular/

On Behalf of Badan Pengurusan Bersama Menara Teega

Appendix 1 : 40,.kWp Solar PV System