Charge+ EV Charging Stations – Phase 2 (23-April’24 Update)

Upon completion of the testing and commissioning by month of March 2024, we should have the following EV chargers at the following locations ;

NEW EV charging points : 8 points

  • Residence carpark next to washing bay (G level carpark)  – 2 charging points x 7.4kW (AC)
  • Suites carpark next to washing bay (G level carpark) – 1 charging point x 11kW (AC)
  • Residence A /Office Tower (G level podium) – 2 charging points x 7.4kW (AC) and 1 charging point x 11kW (AC).
  • Retail carpark (LG parking) – 2 charging points x 60kW (DC).

Existing Charge+ EV charging points at Retail carpark (LG parking) – 2 charging points x 7,4kW (AC).

You can download the Charge+ app from the Appstore or Google Playstore.


DC charger (60kW) is ready for operation.
Location (Public) : https://maps.app.goo.gl/BKKKaL83RD3DEY58A

Smart Dual (7.4kW) AC Charger is ready for operation.
Location (Private) : https://maps.app.goo.gl/6QbrkCpkLaW5HpwB9


Smart (11kW) AC Charger is ready for operation.
Location (Private) : https://maps.app.goo.gl/Gq9UCyVzwzKBdaQZ7


Smart Dual (7.4kW) AC Charger is ready for operation.
Smart (11kW) AC Charger is ready for operation .

Location (Public) : https://maps.app.goo.gl/ufboGj3YYcvY7JmeA